7.39 persons can repair a road in 12 days working 5 hours a day in how many days will 30 persons working 6 hours a day complete a work

Respuesta :

Аноним Аноним
  • 17-07-2018

39 people : 12 days : 5 hours


//Find 1 person

1 person : 12 x 39 days : 5 hours

1 person : 468 days : 5 hours


//Find 30 people:

30 people : 468 ÷ 30 days : 5 hours

30 people : 15.6 days : 5 hours


//Find 1 hour:

30 people : 15.6 x 5 days : 1 hour

30 people : 78 days : 1 hour


//Find 6 hours:

30 people : 78 ÷ 6 days : 6 hours

30 people : 13 days : 6 hours


Answer: 13 days


Answer Link

Otras preguntas

What is measure of angle KJL
Two possible floor plans for a new bathroom are shown. Is there a value for x for which the perimeters are equal? What is the linear equations?
Please help me I will give you the brain thing and extra points. 2/9 image below
Butanol was used in the production of: O Cordite O Nitroglycerin O Fizzy beverages Synthetic rubber
16 Divide by 41 to the nearest 10th
3. ¿Qué está pasando ahora en el Estadio Camp Nou de Barcelona?
HELP ME PLZZ ITS DUE TODAY JUST HELP ME OUT
10 builders can build a house in 20 days. How many builders will you need build the house in 10 days?
please help...i have 25 mins....thanks
Why do people join groups? (Use key terms: bonds, moral, message, purpose)