activity b has a duration of 12 days and an earliest finish (ef) of 22 days. if b's latest start (ls) is 15 days, this must mean that b's slack (in days) is

Respuesta :

Otras preguntas

How does gossip affect the reader’s perception of Daisy Miller? Your answer should be at least 150 words.
what is one sound device in a dream within a dream??​
In 1972, the Watergate break-in occurred at the offices of the Democratic National Committee. Special Prosecutor Archibald Cox. the Committee to Re-Elect the Pr
5 boys gathered leaves. Each boy filled 2/3 of his bag with leaves. How many bags of leaves in all did the 5 boys collect?
solve the following system of equations using substitution y=x+4 3x+5y=36
The distinctive feature of the psychodynamic perspective is its emphasis on a. natural selection.b. brain chemistry.c. unconscious conflicts.d. learned behavior
Which economic activity has largely driven development of modern Southeast Asian cities? Drag the country to the correct box. Vietnam Singapore Malaysia Economi
Dave uses the functionP(d) = 20d - 20 to calculate the net profit of his dog walking business. Where P(d) is the net profit in dollars, and "d" the number of do
What happened at the party convention for the Democrats that affected the 1860 presidential election
What should be current before a Windows Defender scan is run? A. Automatic Maintenance B. File History C. Hard disk partitions D. Drivers for antivirus softwa